JTL employed between 5-7 Operatives on this project which was dependant on programme and working scope.

The stringent quality controls in place and the presence of a permanent on-site Painting Inspector throughout the works, ensured work was completed to specification on time with zero snags.

Jack Tighe Ltd was awarded this Industrial Painting Contract by Balfour Beatty towards the end of 2023. Jack Tighe Ltd commenced their works in July 2024 and completed the project in June 2025.

This project involved the surface preparation and recoating of the whole Barking Barrier Gate 3, London E6 7FF. The Thames Barrier & Associated Gates (TBAG) have been in operational use continuously since they were brought into service in the 1980s and was constructed as part of the Thames flood defence system. The Barking Barrier is just one of the Associated Gates.  

The project was delivered by the Integrated Delivery Team comprising Balfour Beatty, Jacobs, and Environment Agency. The works carried out at Barking Barrier were part of Thames Estuary Assets Management Plan TEAM2100 programme.

The Barking Barrier Gate 3 is 40 metres wide and 11 metres high. The two towers at the side reach 58.8 metres in height.

In order for JTL to carry out works on the gate, there was a requirement to install a bespoke temporary works design which included fully encapsulated hanging scaffold with drainage system to prevent wastewater from UHP water jet washing entering the river Roding.

Access to the site was via the East and West sides of the river Roding. The two sides are not connected for vehicular access and is only by foot. 

All Jack Tighe Ltd operatives received a site induction from Balfour Beatty to ensure safe working practices and site minimum PPE requirements are complied with. Site induction will cover all emergency arrangements on site including Muster points competency of supervisors and operatives. 

Access to our working areas were via designated walkways leading to the fully fixed encapsulated scaffolding which was supplied and maintained by Balfour Beatty. Balfour Beatty also provided permit to work prior to any work commencement.

Also prior to any work commencement, JTL submitted the following documentation to Balfour Beatty for approval:

  • Work Package Plan (WPP) and Task Briefing Sheets (Risk Assessment and Method Statement)
  • Inspection Test Plan (ITP)
  • Pre Start Sub-Contractor Meeting
  • Specific Trade Competency Evidence. 
  • Setting People to Work (DABs/NABs)
  • Sequence of Work Programme
  • Demonstration of Competence Form Completion 
  • Balfour Beatty Health Assessment Questionnaire for Operatives 
  • Lifting Plans for mechanical lifting operations/deliveries on site

Contractor Daily Activity Briefing (DABs) were delivered to all Operatives by SSSTS qualified Site Supervisors. The main aim of the daily briefings was to highlight the shift working activities and associated risk.

Weekly Collaborative Planning Meetings were held to review Health and Safety, quality and general progress. Weekly inspection and toolbox talks were submitted during this meeting, contributing towards the Balfour Beatty digital BIM Plan.

Jack Tighe Ltd.’s Specification Procedure and various working areas:

Main Works

  • Wash down to remove surface contaminants, degrease, and remove a loose coating.
  • Ultra High-Pressure Hydro Blasting (UHP) to remove existing coating to achieve a HB 2½ Standard.
  • Blast clean to BS EN ISO 8501-1:2007 Standard Sa2½. 
  • If flash rusting has occurred, sweep blast to remove to achieve blast cleanliness standard, then the primer will be applied within the same shift.
  • Apply one coat of Intergard holding primer 269 to achieve 50 microns dry film thickness (105 wet film thickness). 
  • Apply one coat of Interzone 954GF to achieve 250 microns dry film thickness (295 wet film thickness). 
  • Apply stripe coat by spray using Interzone 954GF to all areas. All spray applied stripe coat will be worked in with brushes onto all angles, welds, edges, fixings, rivets and all vulnerable areas.
  • Apply second coat of Interzone 954 to achieve 250 microns dry film thickness (295 wet film thickness). 

 

Note – Mastic Application – any areas that can’t be bridged by paint, must be bridged by mastic using Arbokol 1000 applied with a caulking gun. All areas to be agreed before application and instructed to JTL by Balfour Beatty. BB and Jacobs to confirm whether the Arbokol 1000 is to be applied after the stripe coat and then overcoated or as a final application on top of the topcoat.

Galvanised Handrails & Ladders

  • Wash down to remove surface contaminants, degrease, and remove a loose coating.
  • Sweep blast to remove existing coating system.
  • Apply one coat of Intergard holding primer 269 to achieve 50 microns dry film thickness (105 wet film thickness). 
  • Apply one coat of Interzone 954GF to achieve 250 microns dry film thickness (295 wet film thickness). 
  • Apply second coat of Interzone 954 to achieve 250 microns dry film thickness (295 wet film thickness). 

East and West side ladder Rungs on the South side of Barking Barrier Gate 3

  • Prepare and apply coatings as per the main works above.  
  • Apply thin coat of Interzone 954 as per manufacturers recommendations. 
  • Apply GPA 900 Medium Aggregate whilst the paint is still wet.
  • Apply second thin of Interzone 954 to seal the aggregate in as per manufacturers recommendations.

Procedure for repreparation and/or reapplication of paint to the above areas following Submersion in water

  1. Areas previously UHP washed only & blast cleaned to Sa2½ will require rewashing (Low Pressure Jet Washing – Under 5000psi) and reblasting back to Sa2½.
  2. Areas primed with Intergard 269 which are immersed within 24 hours will require rewashing (Low Pressure Jet Washing – Under 5000psi), reblasting back to Sa2½ and reapplication of primer.
  3. Area applied with Interzone 954GF (2 hours curing before immersion) with no discolouration will require a washdown and continue with the specification as per the above and ITP. 
  4. Area applied with Interzone 954GF (2 hours curing before immersion) which have discoloured will require washdown and hand abrade before applying topcoat.
  5. Areas where Interzone 954 topcoat has been applied and discoloured will require washdown, hand abrade and reapplication of the topcoat. 

 

Note – the minimum time for immersion of coatings after application is 2 hours. Therefore, even in the case of a 6 hour emergency warning of a gate closure, there should never be a situation when coating applied are immersed within 2 hours. Simple instruction to cease all coating operations with immediate effect on notification of an emergency gate closure. 

Wheel Box

  • Mechanically clean agreed areas to BS EN ISO 8501-1:2007 Standard St3 as per the photograph below.
  • Apply one coat of interzone 954GF to achieve 250 microns dry film thickness (295 wet film thickness). 
  • Apply second coat of interzone 954 to achieve 250 microns dry film thickness (295 wet film thickness).

The main constraints associated with the site and applicable to Balfour Beatty/JTL were:

  • Compliance with the identified permits were from the Port of London

Authority (PLA), Marine Management Organisation (MMO), Thames Water (TW),

Environment Agency (EA);

  • Small site working area – land available for the site equipment was limited
  • Live Operational Site
  • Navigable Channel
  • 6 Hour Rule – JTL had to allow the Environment Agency to operate the gate within 6 hours notice.

JTL employed between 5-7 Operatives on this project which was dependant on programme and working scope.

The stringent quality controls in place and the presence of a permanent on-site Painting Inspector throughout the works, ensured work was completed to specification on time with zero snags.

Road Haulage Association
Marine Painting Forum
British Safety Council Member
Official NHSS Logo
Train the Painter
Driver CPC Logo
© 2026 Jack Tighe Ltd. ALL RIGHTS RESERVED.